Before a single line is drawn, the architect and engineer must understand the client brief — a detailed statement of the client's requirements, budget, timeline, and expectations. A poorly captured brief leads to redesigns, cost overruns, and disputes.
What is the total plot area and location?
What type of building is required? (Residential / Commercial / Industrial)
How many floors are required?
What is the total budget?
What is the expected carpet area / built-up area?
Are there any special requirements? (Vastu compliance, accessibility, parking)
What is the project timeline?
Are there any religious or cultural preferences for room orientation?
Space Programme — Room-by-Room Area Schedule
The space programme is the list of all rooms, their required areas, and relationships. It is the foundation of the architectural design.
2.1 Typical Space Programme — Residential (G+1 House)
Room / Space
Minimum Area (sqm)
Recommended Area (sqm)
Notes
Living Room
12.0
18.0
Must face north or east — Vastu
Master Bedroom
10.5
14.0
Attached toilet preferred
Bedroom 2
9.0
12.0
Children's room
Bedroom 3
9.0
12.0
Guest room
Kitchen
5.0
8.0
Near dining, east side preferred
Dining Area
7.0
10.0
Adjoining kitchen and living
Toilet / Bathroom
2.5
4.0
Each unit — minimum NBC
Pooja Room
2.0
3.0
North-east corner — Vastu
Staircase
4.5
6.0
Min width 1.0m — NBC
Lobby / Corridor
2.0
3.0
Min 0.9m width
Balcony
2.0
4.0
Optional
Parking (car)
12.0
16.0
Per car — NBC requirement
Servant Room
5.0
7.0
Optional
BUA = Sum of all room areas + wall thickness area + staircase + balcony + common areas
Carpet Area = BUA − (Wall thickness area + Balcony + Common passages)
Loading...
CH 1 — IS CODES & STANDARDS (PART A)
MARKER LEGEND
1. IS 456: PLAIN & REINFORCED CONCRETE
One‑liner — “IS 456 is the main RCC bible for slabs, beams, columns, footings and concrete workmanship on building projects.”
M3 structural thumb rules: slab thickness, beam depth, column size, concrete grades, cover.
M7 QA/QC pre‑pour checklist: cover blocks, w/c ratio, vibration, curing, construction joints.
Example:
You check slab thickness ≈ span/32 (150 mm for 4 m span) and cover 20 mm because IS 456 gives minimum thickness and nominal cover.
Model answer: “RCC design and site practice are mainly as per IS 456:2000, including member sizes, concrete grades, cover, joints and curing requirements.”
2. IS 875 (PARTS 1–3): LOADS ON BUILDINGS
Part 1: Dead Loads
Part 2: Imposed (Live) Loads
Part 3: Wind Loads.
One‑liner — “IS 875 tells us how much load to consider on slabs, beams and columns – dead, live and wind.”
Dead load of 150 mm RCC slab ≈ 3.75 kN/m².
Residential live load = 2.0 kN/m², office 3–4 kN/m².
Rudrapur basic wind speed = 47 m/s (IS 875 Part 3), and seismic zone IV from IS 1893 is also referenced there.
Model answer: “Dead and live loads are as per IS 875 Parts 1 and 2, and wind load is as per IS 875 Part 3.”
3. IS 1893: EARTHQUAKE RESISTANT DESIGN
One‑liner — “IS 1893 tells us how to design for earthquakes – zone factor, response spectra and seismic forces.”
Example on site:
When interviewer asks why you used M25 for columns, you say: “Because project is in Zone IV as per IS 1893, so we prefer M25 and proper ductile detailing.”
4. IS 1904 & IS 1892: FOUNDATIONS AND SOIL INVESTIGATION
IS 1892 — Code of practice for sub‑surface investigations for foundations.
IS 1904 — Design and construction of foundations in soils: general requirements.
One‑liner — “IS 1892 tells us how to do soil investigation, and IS 1904 tells us how to design foundations based on SBC and soil type.”
Soil investigation step mentions IS 1892 (minimum 2 boreholes, SBC and water table).
Soil investigation table gives SBC values (120–200 kN/m²) and footing recommendations based on soil type.
In M3, footing size and depth thumb rules (SBC, 150–200 kN/m²) are guided by IS 1904.
5. IS 1200: MEASUREMENT & BOQ
One‑liner — “IS 1200 is the measurement bible for BOQ and billing – how to measure RCC, brickwork, plaster, flooring, etc.”
All MB sheets are explicitly “IS 1200 compliant” for all elements.
BOQ Master, RA Bills, Final Bill and Reconciliation depend on these measurement rules.
Examples:
You know beams and columns are measured in m³, brickwork in m³, plaster and flooring in m², centering in m², etc., following IS 1200.
Model answer: “All quantities and MBs are prepared as per IS 1200 method of measurement, to keep BOQ and billing standard.”
6. IS 516 & IS 1199: CONCRETE TESTS (CUBES & SLUMP)
IS 516:1959 — Method of Tests for Strength of Concrete (cube tests).
IS 1199:1959 — Methods of Sampling and Analysis of Concrete (slump/workability).
One‑liner — “IS 516 is for cube strength tests and IS 1199 is for slump and fresh concrete tests.”
Concrete cube test register is explicitly labelled IS 516 + IS 456.
Slump test register is labelled IS 1199.
Pre‑pour checklist: 3 cubes per 5 m³, slump test before pour.
Example:
You record 7‑day and 28‑day strengths for M20; acceptance criteria from IS 456, test method from IS 516.
You keep slump 25–50 mm for columns and 100–150 mm for pumped slabs per your register guided by IS 1199.
7. IS 383 & IS 1786: AGGREGATES AND REINFORCEMENT STEEL
IS 383 — Specification for coarse and fine aggregates from natural sources.
IS 1786 — High strength deformed steel bars and wires for concrete reinforcement.
One‑liner — “IS 383 is for sand and aggregate quality, IS 1786 is for Fe500 reinforcement bars.”
Material tests for sand and aggregates refer to grading, silt, cleanliness as per IS 383.
Steel grade Fe500 is referenced in M3 structural calculator and BBS assumptions as per IS 1786.
Example:
When you check a TMT bundle, you verify Fe500 on the mill test certificate as per IS 1786.
For sand, you check for organic impurities and silt content guided by IS 383.
8. NBC 2016 & IS 962: PLANNING, FAR, ROOM SIZES
REFERENCES —
NBC 2016 — National Building Code of India.
IS 962:1989 — Code of practice for architectural and building drawings (and room sizes).
One‑liner — “NBC and IS 962 give rules for planning, setbacks, heights, room sizes and general building requirements.”
Setback requirements and FAR limits are from NBC tables.
Standard room sizes and heights (living, bedroom, kitchen, toilets) are labelled with IS 962 and NBC.
Example:
You check if a 3.6 m × 3.0 m living room with 2.75 m height meets minimum area and height from NBC/IS 962.
FAR and ground coverage are auto‑checked against NBC ranges in your sheet.
9. IS 4021 & IS 1038: DOORS AND WINDOWS
IS 4021 — Timber door, window and ventilator frames and shutters (sizes and construction).
IS 1038 — Steel/wood windows and ventilators.
One‑liner — “IS 4021 and IS 1038 give standard sizes and construction details for doors, windows and ventilators.”
Main door 1.0–1.2 m × 2.1 m, internal doors 0.9 m × 2.1 m, toilet doors 0.75 m × 2.1 m are referenced with IS 4021.
Bedroom, kitchen and toilet windows and ventilators sizes are referenced with IS 1038.
10. IS 18001 / ISO 45001, IS 3764, IS 11057, IS 3696, IS 818: SAFETY
KEY SAFETY CODES/REFERENCES —
IS 18001 / ISO 45001 — Occupational Health and Safety Management Systems.
IS 3764 — Safety in excavation work.
IS 11057 & IS 3696 — Safety in scaffolds, ladders, and working at height.
IS 818 — Safety in welding.
Indian Electricity Rules 1956 — Electrical safety.
One‑liner — “Safety codes cover systems (IS 18001) plus specific high‑risk activities: excavation, height work, scaffolding, lifting, welding and electrical.”
Daily toolbox talks mention IS 3764, IS 11057, IE Rules.
Activity‑wise safety checklist maps each activity to its IS/NBC reference (excavation, height, concrete, steel, electrical, welding, scaffolding, lifting).
Example:
For excavation >1.5 m, you mention shoring, safe slopes and access ladder as per IS 3764.
For scaffolding, you ensure base plates, bracing and inspection tags as per IS 11057/IS 3696.
Model answer: “We follow IS 18001/ISO 45001 for safety management and specific IS codes like IS 3764 for excavation, IS 11057/3696 for scaffolding and height work, IS 818 for welding and IE Rules 1956 for electrical safety.”
11. PROJECT & CONTRACT SIDE: RA BILLS, CLAIMS, DLP
Here codes are fewer, but standard practices are set by government rules and contract forms.
REFERENCES IN YOUR SYSTEM —
MBs and BOQ: IS 1200.
Labour: Construction Workers Act 1996, EPFO/ESIC rules referenced in M9 sheets.
DLP and retention: industry practice used in your DLP tracker.
One‑liner — “Measurement is IS 1200; RA bills, final bills and claims follow contract conditions (CPWD/FD, FIDIC etc.) plus labour and tax laws.”
RA Bills, Final Bill, Tax Invoice and Payment Certificate are structured to match Indian contract practice (mobilisation advance, retention 5%, DLP 12 months).
Claims and Rate Variation sheets reflect EOT, escalation and disruption records.
12. HOW TO DROP CODES FLUENTLY IN ANSWERS
Pattern you should follow:
Name the activity.
Name the code.
Give one concrete example (number, check, or site action).
Examples using your own sheets:
“For RCC we follow IS 456 and IS 875; example, for a 4 m slab we keep about 150 mm thickness and design for 2 kN/m² live load from IS 875 Part 2.”
“Quality is checked by slump test as per IS 1199 and cube test as per IS 516, and we accept concrete as per IS 456 criteria.”
“Measurement and BOQ are as per IS 1200; for example, brickwork is in cubic metre, plaster in square metre, as reflected in my MB and BOQ sheets.”
Ch 1 — IS Codes & Standards (Part B)
1. RCC DESIGN & LOAD CODES
1.1 Quick reference table — structural core
Code
Full name
One‑line use
Example from your sheets
IS 456:2000
Plain & Reinforced Concrete – Code of Practice
Main RCC code for slabs, beams, columns, footings, workmanship, durability and acceptance criteria.
M3 structural thumb rules (slab thickness, beam depth, column sizes, cover, concrete grade) and M7 pre‑pour checklist and cube acceptance are all based on IS 456.
IS 875 Part 1
Design Loads – Dead Loads
Gives dead load values for RCC, brickwork, floor finish, false ceiling etc.
M3 uses 3.75 kN/m² for 150 mm slab and wall weights per metre run from IS 875 Part 1.
IS 875 Part 2
Design Loads – Imposed (Live) Loads
Gives live load for residential, office, stairs, roofs.
M3 uses 2.0 kN/m² for residential floors, 3–4 kN/m² for office floors.
IS 875 Part 3
Wind Loads
Gives basic wind speed and method to calculate wind pressure.
Rudrapur wind speed 47 m/s noted in M3; used when explaining why high‑rise needs proper wind design.
IS 1893
Earthquake Resistant Design of Structures
Defines seismic zones, response spectra and design seismic forces.
M3 calls Rudrapur Zone IV and recommends M25 for columns in high seismic zone.
IS 1904
Design & Construction of Foundations
General requirements for foundation design based on soil and SBC.
M3 footing size/depth thumb rules (SBC 150–200 kN/m²) align with IS 1904 guidance.
IS 1892
Sub‑surface Investigation for Foundations
How to do soil investigation, boreholes, SPT, SBC, water table.
M4 soil investigation step explicitly references IS 1892 and soil investigation table (BH‑1, BH‑2, BH‑3).
Interview use:
“In design we mainly follow IS 456, IS 875 Parts 1–3, IS 1893 for seismic and IS 1904/1892 for foundations and soil investigation.”
2. QA/QC, CONCRETE & MATERIAL CODES
2.1 Concrete QA/QC
Code
Full name
One‑line use
Example from your sheets
IS 516:1959
Method of Tests for Strength of Concrete
Cube compression test method for 7‑day, 28‑day strength.
M7 concrete cube test register is titled IS 516 + IS 456; all cube strengths recorded as per this code.
IS 1199:1959
Methods of Sampling and Analysis of Concrete
Slump test and other fresh concrete tests.
M7 slump test register explicitly references IS 1199 and gives acceptable ranges for columns, foundations and slabs.
IS 456:2000
Plain and Reinforced Concrete
Also gives concrete acceptance criteria, cover, curing, joints.
M7’s “Concrete Acceptance Criteria” table for M15–M30 is based on IS 456 (fck, w/c, slump limits).
IS 14687 (ref.)
Formwork / falsework guidance (plus IS 456 clauses)
Alignment, support, stripping time for formwork.
Pre‑pour checklist item “Shuttering alignment” cites IS 14687 and IS 456.
2.2 Material quality
Code
Full name
One‑line use
Example from your sheets
IS 383
Coarse and Fine Aggregates from Natural Sources
Quality, grading and limits for sand and aggregates.
M7 material tests and assumptions for sand/aggregate cleanliness and grading are aligned to IS 383.
IS 1786
High Strength Deformed Steel Bars and Wires
Grade and properties of Fe415/Fe500 bars.
M3 uses Fe500 and cover rules with design based on IS 456, steel spec from IS 1786.
IS 269, IS 1489
Ordinary & Portland Pozzolana Cement
Requirements for OPC and PPC.
Cement quality checks in your QA/QC notes (manufacturing date, storage) follow these standards as background.
Interview use:
“For concrete QA we rely on slump test as per IS 1199, cube tests as per IS 516 and acceptance criteria as per IS 456.”