Ch 13 INTERIOR FIT-OUT AND FINISHING WORKS
CHAPTER — INTERIOR FIT-OUT AND FINISHING WORKS
MARKER LEGEND
DATA TABLE — Reference table with codes, rates, values
WHAT IS INTERIOR FIT-OUT
Interior fit-out is the process of making the interior of a building suitable for occupation after the structure is complete. It covers all works from plaster to final handover including flooring, ceiling, painting, joinery, MEP finishing, and furniture installation.
Fit-out is broadly classified into three types:
Shell and Core — only structural frame and external envelope complete, no internal finishing
Cat A (Category A) — basic finishing done, raised floor, false ceiling, lighting, HVAC grilles, toilets
Cat B (Category B) — full tenant-specific fit-out including partitions, branding, furniture, AV systems
SEQUENCE OF INTERIOR FINISHING WORKS
The correct sequence on site must be followed to avoid rework and damage:
Step 1 — Internal Plaster (walls and ceiling)
Step 2 — Waterproofing (toilets, wet areas, terrace)
Loading...
Get Notion free
MARKER LEGEND
DATA TABLE — Rates / tolerances / reference values
1. WHAT IS INTERIOR FIT-OUT
Interior fit-out is the process of converting a completed structure (shell) into a usable, occupiable space by executing all internal finishing works like plaster, flooring, false ceiling, painting, joinery, MEP finishing and furniture.
Types of fit-out:
Shell and Core — Only structural frame and external envelope completed, no internal finishing.
Cat A — Basic landlord finishing: raised floor, false ceiling, basic lighting, HVAC grilles, toilets ready.
Cat B — Tenant-specific interior: partitions, cabins, branding, furniture, AV systems, detailed interior design.
2. CORRECT SEQUENCE OF INTERIOR FINISHING WORKS
Always follow a proper sequence to avoid damage, rework, and abortive costs.