Ch 10 — Contract Management & Billing
Ch 10 — Contract Management & Billing
Construction Engineer Master Reference | RahulNew 2026
─────────────────────────────────────────────────────────────────────────────────────
What Is a Construction Contract?
A construction contract is a legally binding agreement between the owner (employer/client) and the contractor that defines the scope of work, price, time, quality, and responsibilities of each party. Every site engineer must understand the contract because it governs payment, variations, disputes, and liability.
Offer and acceptance — both parties agree on scope and price
Consideration — payment in exchange for work
Competency — both parties legally capable of contracting
Free consent — no coercion, fraud, or misrepresentation
Lawful object — the work must be legal
In India, construction contracts are governed by the Indian Contract Act 1872 and the specific contract documents agreed between the parties.
Types of Construction Contracts
Contract Type
Basis of Payment
Risk
Best Suited For
Example
Lump Sum (Fixed Price)
Fixed total amount for entire scope
Contractor bears cost risk
Well-defined scope with complete drawings
Residential building with final BOQ
Item Rate / Unit Price
Rate per unit — paid on actual quantity executed
Client bears quantity risk
Civil works where quantities may vary
Road, dam, foundation — CPWD/PWD contracts
Cost Plus / Reimbursable
Actual cost + agreed fee (% or lump)
Client bears all cost risk
Emergency works, undefined scope
Disaster repair, renovation with unknowns
Percentage Rate
Contractor quotes % above/below Schedule of Rates
Moderate shared risk
Government works using DSR/SSR
CPWD, MES, state PWD contracts
EPC (Turnkey)
Fixed price for design + procure + construct
Contractor bears all risk
Industrial, infra — single responsibility
Power plant, chemical plant, highway
GMP (Guaranteed Maximum Price)
Max price agreed — saving shared
Shared risk
Commercial buildings, fast-track projects
Shopping mall, hotel
BOT / BOOT
Build + Operate + Transfer after concession
Private developer risk
Large infrastructure — roads, bridges
NHAI toll roads, metro rail
Contract Documents — Hierarchy
When a dispute arises, the contract documents govern. The hierarchy determines which document takes precedence if there is a conflict.
Priority
Document
Contents
Governs
1 — Highest
Letter of Award / Contract Agreement
Parties, project, price, dates
Overall agreement — overrides all others
2
Special Conditions of Contract (SCC)
Project-specific deviations from GCC
Any special terms agreed for this project
3
General Conditions of Contract (GCC)
Standard clauses — payment, variation, dispute, EOT
Standard legal framework
4
Specifications
Materials, workmanship, testing requirements
Technical quality requirements
5
BOQ / Schedule of Rates
Items, units, quantities, rates
Measurement and payment
6
Drawings
Architectural, structural, MEP drawings
Physical scope and dimensions
7 — Lowest
Correspondence
Pre-contract letters, clarifications
Intent — reference only
Key Contract Clauses Every Engineer Must Know
Clause
What It Covers
Engineer's Relevance
Scope of Work
Exact description of what is included and excluded
Know what you are responsible to deliver
Contract Price
Total agreed price — lump sum or item rate schedule
Baseline for all billing and variation
Payment Terms
When bills are submitted, when payment is made
Cash flow planning and RA bill schedule
Mobilisation Advance
Advance payment at start — typically 10-15% of contract value
Recovered from RA bills — track recovery
Retention
Amount withheld from each bill — typically 5-10%
Released 50% at completion, 50% after DLP
Variation / Change Order
How changes to scope are authorised and valued
Every change needs written VO before execution
Extension of Time (EOT)
Right to extend completion date for valid reasons
Submit EOT claim with evidence and programme impact
Liquidated Damages (LD)
Penalty per day/week for late completion
Know the LD rate — it is a financial risk
Defects Liability Period (DLP)
Period after completion during which contractor fixes defects
Typically 12 months — retention held until end
Force Majeure
Events beyond both parties control that excuse performance
COVID, flood, earthquake — EOT granted but no cost
Dispute Resolution
How disputes are settled — arbitration, mediation, court
Follow the procedure — do not go direct to court
Termination
Conditions under which contract can be ended by either party
Know notice periods and grounds for termination
Get Notion free
MARKER LEGEND
1. CONTRACT STRUCTURE & FLOW OF MONEY
A construction contract is basically a promise to deliver BOQ scope in a defined time, for defined rates, with defined payment terms and risk‑sharing.
Your V5 implements the full chain:
BOQ Master → RA Bills 1–2 → Final Bill → Tax Invoice → Payment Certificate → Bill Status.
Cash Flow (M6) shows planned vs actual money movement.
Reconciliation, Rate Variation, Claims, DLP tracker show back‑end control.
IS / LAW — IS 1200 for measurement, CPWD style contracts and DSR for rate structure, GST laws for tax, labour laws for PF/ESI.
2. BOQ, MB & RA BILLS: HOW THEY LINK
All billing must be backed by measurement in MB using IS 1200, then linked to BOQ and RA Bills.