Home / Civil Construction Guide / Chapter 10: Contracts, Contractor Billing & Claims Management
Chapter 10 • Billing & RA Bills

Contracts, Contractor Billing & Claims Management

Running Account (RA) Bill Verification, Measurement Books, Deductions & Variations

Er. Rahul Saxena (B.Tech Civil) IS Codes & CPWD Compliant Peer-Reviewed Field Practice

Ch 10 — Contract Management & Billing

Ch 10 — Contract Management & Billing

Construction Engineer Master Reference  |  RahulNew 2026

─────────────────────────────────────────────────────────────────────────────────────

What Is a Construction Contract?

A construction contract is a legally binding agreement between the owner (employer/client) and the contractor that defines the scope of work, price, time, quality, and responsibilities of each party. Every site engineer must understand the contract because it governs payment, variations, disputes, and liability.

Must Know Principle
MUST KNOW — The five essentials of a valid contract:

Offer and acceptance — both parties agree on scope and price

Consideration — payment in exchange for work

Competency — both parties legally capable of contracting

Free consent — no coercion, fraud, or misrepresentation

Lawful object — the work must be legal

In India, construction contracts are governed by the Indian Contract Act 1872 and the specific contract documents agreed between the parties.

Types of Construction Contracts

Contract Type

Basis of Payment

Risk

Best Suited For

Example

Lump Sum (Fixed Price)

Fixed total amount for entire scope

Contractor bears cost risk

Well-defined scope with complete drawings

Residential building with final BOQ

Item Rate / Unit Price

Rate per unit — paid on actual quantity executed

Client bears quantity risk

Civil works where quantities may vary

Road, dam, foundation — CPWD/PWD contracts

Cost Plus / Reimbursable

Actual cost + agreed fee (% or lump)

Client bears all cost risk

Emergency works, undefined scope

Disaster repair, renovation with unknowns

Percentage Rate

Contractor quotes % above/below Schedule of Rates

Moderate shared risk

Government works using DSR/SSR

CPWD, MES, state PWD contracts

EPC (Turnkey)

Fixed price for design + procure + construct

Contractor bears all risk

Industrial, infra — single responsibility

Power plant, chemical plant, highway

GMP (Guaranteed Maximum Price)

Max price agreed — saving shared

Shared risk

Commercial buildings, fast-track projects

Shopping mall, hotel

BOT / BOOT

Build + Operate + Transfer after concession

Private developer risk

Large infrastructure — roads, bridges

NHAI toll roads, metro rail

Practical Site Method
SITE PRACTICE: Even on small residential projects, always have a written contract with scope, drawings, rate, payment terms, and retention clearly stated. Verbal contracts lead to disputes every time.

Contract Documents — Hierarchy

When a dispute arises, the contract documents govern. The hierarchy determines which document takes precedence if there is a conflict.

Priority

Document

Contents

Governs

1 — Highest

Letter of Award / Contract Agreement

Parties, project, price, dates

Overall agreement — overrides all others

2

Special Conditions of Contract (SCC)

Project-specific deviations from GCC

Any special terms agreed for this project

3

General Conditions of Contract (GCC)

Standard clauses — payment, variation, dispute, EOT

Standard legal framework

4

Specifications

Materials, workmanship, testing requirements

Technical quality requirements

5

BOQ / Schedule of Rates

Items, units, quantities, rates

Measurement and payment

6

Drawings

Architectural, structural, MEP drawings

Physical scope and dimensions

7 — Lowest

Correspondence

Pre-contract letters, clarifications

Intent — reference only

Must Know Principle
MUST KNOW: In CPWD and PWD contracts, the GCC (General Conditions of Contract) is the primary legal document. Know its key clauses — payment, variation, defects, dispute.

Key Contract Clauses Every Engineer Must Know

Clause

What It Covers

Engineer's Relevance

Scope of Work

Exact description of what is included and excluded

Know what you are responsible to deliver

Contract Price

Total agreed price — lump sum or item rate schedule

Baseline for all billing and variation

Payment Terms

When bills are submitted, when payment is made

Cash flow planning and RA bill schedule

Mobilisation Advance

Advance payment at start — typically 10-15% of contract value

Recovered from RA bills — track recovery

Retention

Amount withheld from each bill — typically 5-10%

Released 50% at completion, 50% after DLP

Variation / Change Order

How changes to scope are authorised and valued

Every change needs written VO before execution

Extension of Time (EOT)

Right to extend completion date for valid reasons

Submit EOT claim with evidence and programme impact

Liquidated Damages (LD)

Penalty per day/week for late completion

Know the LD rate — it is a financial risk

Defects Liability Period (DLP)

Period after completion during which contractor fixes defects

Typically 12 months — retention held until end

Force Majeure

Events beyond both parties control that excuse performance

COVID, flood, earthquake — EOT granted but no cost

Dispute Resolution

How disputes are settled — arbitration, mediation, court

Follow the procedure — do not go direct to court

Termination

Conditions under which contract can be ended by either party

Know notice periods and grounds for termination

Get Notion free

MARKER LEGEND

Must Know Principle
MUST KNOW — Core concept, every job / every interview
Key Formula
FORMULA — Key calculation / method
IS Standard
IS CODE / LAW — Standard or legal reference
Practical Site Method
SITE PRACTICE — Real execution method
GCC & Technical Interview Q&A
INTERVIEW TAG — High-probability interview Q&A
Common Contractor Mistake
COMMON MISTAKE — Frequent error by fresh engineers
Field Thumb Rule
THUMB RULE — Quick practical shortcut

1. CONTRACT STRUCTURE & FLOW OF MONEY

A construction contract is basically a promise to deliver BOQ scope in a defined time, for defined rates, with defined payment terms and risk‑sharing.

Your V5 implements the full chain:

BOQ Master → RA Bills 1–2 → Final Bill → Tax Invoice → Payment Certificate → Bill Status.

Cash Flow (M6) shows planned vs actual money movement.

Reconciliation, Rate Variation, Claims, DLP tracker show back‑end control.

IS / LAW — IS 1200 for measurement, CPWD style contracts and DSR for rate structure, GST laws for tax, labour laws for PF/ESI.

GCC & Technical Interview Q&A
INTERVIEW TAG — “Explain the complete billing cycle in a construction project from BOQ to final payment.”
Field Thumb Rule
THUMB RULE — Contract = Scope + Time + Cost + Quality + Safety + Risk sharing; any dispute will be about at least one of these.

2. BOQ, MB & RA BILLS: HOW THEY LINK

All billing must be backed by measurement in MB using IS 1200, then linked to BOQ and RA Bills.

Direct Engineering Assistance